Tuesday, February 8, 2011

Dragon Ball Z Kamehasutra 2

NEW MUNICIPAL BUILDING IN CONSTRUCTION

The Municipality of Ambato construct the new municipal building. The work is performed under to plan and record progress of 10.03% of the work. The council invests 4 million 514 thousand 610 U.S. dollars, in an area of \u200b\u200b16,096 meters square. The contractor is Alvaro Guamán. The project is designed in three blocks: A block of four floors and 5 floors. In addition, two parking areas, one in the basement for 80 vehicles and one on the ground floor for 104 vehicles.


When you ran the Eastern block wall, central block wall, left side wall of the parking underground shaft columns 1 to 6 of the Eastern bloc, plinths for 6 columns in the central block, in the south block is built plinths for 10 columns, steel reinforcement and ready-mixed concrete plant.

0 comments:

Post a Comment