Rv: JUAN LEON MERA BRIDGE
From: Diana Molina Saenz (gata_bellita@yahoo.es)
Sent: Tuesday, 16
March 2010 17:05:56 To: mach1959@hotmail.com
Lords CITIZEN WATCH PUBLIC WORKS
Ambato.
What is the reason for the Municipality of Ambato and construction company, until now, have made the delivery receipt of the work?
Sincerely,
SAENZ DIANA MOLINA
gata_bellita@yahoo.es
GUEST EXPERT
Carranza Marcelo Ortega
ARCHITECT AND MASTER
Primary: School "Abdon Calderon"
School: Colegio Juan Leon Mera La Salle High
: Central University of Ecuador, UCE
Universidad San Francisco de Quito
Polytechnic Madrid National
works in the field of construction since 1993, weather you're experiencing rapid growth in the market in Ambato and other cities in the region of the country. Builder Orca created to direct and coordinate human and material resources of projects, using modern management techniques. that can achieve predetermined objectives of cost, coverage, time and quality.
ANALYSIS AND COMMENTARY: is a delicate subject. There seems to administrative differences, economic and technical, between the Municipality of Ambato and Herd Construction Crespo. The work cost about five million dollars, funded the Corporacion Andina de Fomento and part community with direct input from the 25% income tax. About what is happening, the legal advisor of the Municipality of Ambato, Dr. Angel Polibio Chaves, explained to the media to enter service after the bridge "Juan León Mera (JLM) in 2009, began organize the provisional acceptance where analyzed administrative and technical issues. In the administrative sector was consulted on how State Attorney General should act in the town of Ambato. In what appeared a few technical differences with the Construction, impossible delivery - provisional acceptance of the work.
view of this, we applied the twenty-third clause of the contract to build the bridge JLM, ie go to a technical arbitration PUCE - Sede Ambato, the Chamber Ambato Trade and Industry Chamber of Tungurahua.
This authority under the contract was notified to the constructure and demand by the municipality would be in progress. The technician said court would consist of one arbitrator appointed by the Mayor, one by the Herd Construction Crespo and a third by mutual agreement of the parties in conflict.
This authority under the contract was notified to the constructure and demand by the municipality would be in progress. The technician said court would consist of one arbitrator appointed by the Mayor, one by the Herd Construction Crespo and a third by mutual agreement of the parties in conflict.
regard to fault, the Municipality and the builders have to acquiesce to arbitration. If the jumper JLM is well constructed, the City should abide, and if he says that the bridge must be repaired, the manufacturer must accept the resolution. On the amount of fines that the municipality has applied to the construction company, the Court will also decide whether or not to apply those penalties.
As everyone knows, the delivery - receipt of a work is a process complicated where the contractor and the contractor will meet the deadlines, financial settlement procedures, the items recorded deficiencies that must be justified in the final acceptance, etc., etc. And, as we noted, the bridge JLM was complicated project implementation and therefore led to these problems.
Ambato community, which is you have the right and obligation to know what is happening with the bridge JLM and demand quality in this and all works. For its part, the municipality simply accept those demands and implement the law, technical standards and creating relevant, moral and ethical. On the case
JLM bridge, we all have to wait for the final ruling of the arbitration.
JLM bridge, we all have to wait for the final ruling of the arbitration.
.